IPP Software Navigation Tools IPP Links Communication Pan-STARRS Links

Changes between Version 60 and Version 61 of MD.PV3


Ignore:
Timestamp:
Jan 3, 2018, 10:45:48 PM (9 years ago)
Author:
Mark Huber
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • MD.PV3

    v60 v61  
    2121___General Summary Status:___
    2222
    23  * 09/20/2017 -- full file scan integrity check summary --
     23 * 09/20/2017 -- full file scan integrity check summary -- will add to [wiki:MD.PV3-MDnotes], [wiki:MD.PV3-CNPnotes]
    2424 * 04/16/2017 -- still on hold -- entire cluster hardware moved Maui->Oahu finished, intermediate product loss to be evaluated and code issues to be addressed over next few months -- will not be loaded into PSPS until after DR2 winter 2018 (only MD01-10, CNP to be done)
    2525
     
    4949
    5050 
    51 == PV3 Processing Plan ==
     51== PV3 Plan ==
     52
     53camera SMF -- mostly finished
     54 * ~0.5wk to finish verification, ready ~mid-January
     55 * can be loaded into DVO once final DR2 code/formats ready and doesn't conflict with DR2 work
     56
     57warp images -- mostly finished
     58 * ~0.5wk to finish verification and setup release tables for postage stamp access -- available ~mid-January
     59
     60ref stack -- mostly finished
     61 * MD: ~1wk to sort out, expect ~mid-January
     62 * CNP: at least ~2wk setup and process, expect ~end January
     63 * release tables for postage stamps -- available ~mid to end January
     64
     65deep stack -- mostly finished
     66 * MD check quality faults -- ~1wk to sort out, ~end January
     67 * CNP check quality faults -- ~1wk to sort out, ~end January
     68 * release tables for postage stamps -- available ~end January
     69
     70night stack --
     71 * need to fix quality fault issue -- ~1-2wk to sort out and reprocess as needed, ~end of February?
     72 * release tables for stamps -- end of February?
     73 
     74iq stack --
     75 * ~1wk setup & 1wk processing -- ~early March?
     76 * release tables for postage stamps -- early March?
     77
     78stack photometry (staticsky+skycal) --
     79 * need all stack products finished, start ~mid to late February
     80 * ~1wk setup and processing
     81 * load catalogs into DVO --
     82
     83full-forced photometry --
     84 * ~2wk setup/testing, ~2wk processing
     85 * need stack photometry finished, ~mid-late Febrary start
     86 * load catalogs into DVO --
     87
     88WS diff --
     89 * MD 95% finished -- ~1wk to verify
     90 * CNP ~1wk to setup+process
     91 * CNP requires refstack to finish, start early February
     92 * load catalogs into DVO --
     93 * no images for postage stamps initially -- unknown image update process
     94
     95SS diff --
     96 * ~1wk to setup/process
     97 * load catalogs into DVO --
     98 * no images for postage stamps initially -- unknown image update process
     99
     100non-PSPS product transfer to STScI (images) -- start as soon as possible when STScI ready
     101 * warps ~ --
     102 * stacks ~ 38TB? -- cannot start until late Febrary/early March
     103 * diffs ~ --
     104 * need to look up ~rate downloading lost MD files earlier --
     105
     106MD+CNP summary paper --
    52107
    53108