| 51 | | == PV3 Processing Plan == |
| | 51 | == PV3 Plan == |
| | 52 | |
| | 53 | camera SMF -- mostly finished |
| | 54 | * ~0.5wk to finish verification, ready ~mid-January |
| | 55 | * can be loaded into DVO once final DR2 code/formats ready and doesn't conflict with DR2 work |
| | 56 | |
| | 57 | warp images -- mostly finished |
| | 58 | * ~0.5wk to finish verification and setup release tables for postage stamp access -- available ~mid-January |
| | 59 | |
| | 60 | ref stack -- mostly finished |
| | 61 | * MD: ~1wk to sort out, expect ~mid-January |
| | 62 | * CNP: at least ~2wk setup and process, expect ~end January |
| | 63 | * release tables for postage stamps -- available ~mid to end January |
| | 64 | |
| | 65 | deep stack -- mostly finished |
| | 66 | * MD check quality faults -- ~1wk to sort out, ~end January |
| | 67 | * CNP check quality faults -- ~1wk to sort out, ~end January |
| | 68 | * release tables for postage stamps -- available ~end January |
| | 69 | |
| | 70 | night stack -- |
| | 71 | * need to fix quality fault issue -- ~1-2wk to sort out and reprocess as needed, ~end of February? |
| | 72 | * release tables for stamps -- end of February? |
| | 73 | |
| | 74 | iq stack -- |
| | 75 | * ~1wk setup & 1wk processing -- ~early March? |
| | 76 | * release tables for postage stamps -- early March? |
| | 77 | |
| | 78 | stack photometry (staticsky+skycal) -- |
| | 79 | * need all stack products finished, start ~mid to late February |
| | 80 | * ~1wk setup and processing |
| | 81 | * load catalogs into DVO -- |
| | 82 | |
| | 83 | full-forced photometry -- |
| | 84 | * ~2wk setup/testing, ~2wk processing |
| | 85 | * need stack photometry finished, ~mid-late Febrary start |
| | 86 | * load catalogs into DVO -- |
| | 87 | |
| | 88 | WS diff -- |
| | 89 | * MD 95% finished -- ~1wk to verify |
| | 90 | * CNP ~1wk to setup+process |
| | 91 | * CNP requires refstack to finish, start early February |
| | 92 | * load catalogs into DVO -- |
| | 93 | * no images for postage stamps initially -- unknown image update process |
| | 94 | |
| | 95 | SS diff -- |
| | 96 | * ~1wk to setup/process |
| | 97 | * load catalogs into DVO -- |
| | 98 | * no images for postage stamps initially -- unknown image update process |
| | 99 | |
| | 100 | non-PSPS product transfer to STScI (images) -- start as soon as possible when STScI ready |
| | 101 | * warps ~ -- |
| | 102 | * stacks ~ 38TB? -- cannot start until late Febrary/early March |
| | 103 | * diffs ~ -- |
| | 104 | * need to look up ~rate downloading lost MD files earlier -- |
| | 105 | |
| | 106 | MD+CNP summary paper -- |